Plan dates, dependencies, sprints and baselines

Plan task dates, dependencies, sprints and retained baselines.

Open in your workspace

Before you start

Build the declared plan

  1. Open the project and Open task plan (#/projects/:projectId/planning).
  2. Select the task using the searched choices. Enter known planned start, canonical due date and manual minutes/points estimates.
  3. Under Dependencies, link the actual blocking task to the blocked task. Self/cross-project/cyclic dependencies are rejected.
  4. An owner/admin selects Planning calendar and Save selected calendar.
  5. Inspect Timeline, its local-date range, milestone/sprint markers, conflict labels and accessible table alternative. The range is bounded to 366 days.

Review a sprint and saved baseline

  1. Create a dated sprint and add/move eligible tasks. Supply a reason for required scope changes.
  2. An owner/admin reviews the exact current forecast and Start sprint.
  3. When closing, propose an explicit outcome for every unfinished task: carry, return to backlog or waive with reason.
  4. A different current owner/admin checks the scope and Approve close or Decline close.
  5. Use Capture baseline after previewing the current plan and compare known dates with a saved baseline.

Expected result

Started/closed scope and baselines are retained. Closing a sprint does not mark incomplete tasks done. Unknown estimates remain unknown; date variance is available only for known dates.

Troubleshooting

Refresh/reselect a stale task before retrying; preserved input is not a current source. Dates do not cascade automatically. Actual effort, capacity, cost and critical path are unavailable.